| June 5, 2007 | - The homestretch is here. Installed the rear seat belts. |
| - Compass installed. | |
| - Data plate installed. | |
| - Parking brake handle completed. | |
| - Cowling center flange finished. | |
| - Cowling augmentationfinishing work. |
| June 24, 2007 | - FAA paperwork is mailed off to Stan Faske in the Cincinnati Flight Standards District Office (FSDO). We removed the whiskey compass (too much interference, it'll probably move overhead). |
| - Moved the BMA EFIS/One's magnetometer to the strake | |
| - Added bumpouts on the keel for the Strong Pitch Trim system (it was limiting aileron deflection slightly) | |
| - Installed trailing edge fences | |
| - Recalibrated the fuel gauges | |
| - Continued work on the cowling | |
| - Started working on the inner door panels. | |
| - 44VF Ready to Run. |